                    DBIS LAB  Project Schedule and Mark Distribution
===========================================================================
Team size: 4 (3 or 5 will be allowed)   
Work estimate: 2hrs/day x 20 days per individual
Implementation Platform(s):
  Client: HTML only (Javascript only if its really useful)
  Server side: Java + JDBC + Servlets
  Database Server: Oracle, MS-SQL server, ...

Tentative Deadlines and Marks Allocation:
  Project Allocation:          Aug 18
  Project Scope Report:        Sep  1        5%
  First Stage Design (SRS):    Sep 15       20%
  Prototype Demo:              Nov 1 and 2  25%
  Final Demo:                  Nov 15-17    50%
===========================================================================