PROJECT REPORT
(FROM 12TH OCTOBER TO 7TH NOVEMBER)
Project work done by:
	Neha Aggarwal
	Poornima Tambe
	Ruchita Pangerkar
	Suhani Jain


	14th October (Thursday)
(Work done by the whole team)
	The topic of the project was decided in the meeting.
	Meeting started at 11.40 and the meeting concluded at 12.20.
	Each of the team was allotted a part of the program.

	At around 6:30 in the evening the team members discussed about the part allotted to them.
	The discussion topics were
1.	Creating the account,
2.	Working system of bank ,
3.	Types of accounts, 
4.	Operating mechanism of account
	The meeting continued for one hour.
	Suhani Jain worked on the project from 3:30 to 5:00 and wrote a program on opening an account individually.






15th October (Friday)
(Work done by the whole team)
	Had gone to Canara Bank for getting details about their functioning to get an idea about how to proceed on the project.
	We stayed there from 12:30 to 1:10
	Modifications were made by Suhani on her part of the project.


16th October (Saturday)
	After the lab a meeting was held for the whole lab batch and the work done by all of us were discussed upon.
	Even some alterations were made in the programme during the lab.
 

17th October (Sunday)
	A group meeting was held today.
	The programme was further worked upon.
	The meeting carried on till 2 hours and 10 minutes starting from 4:20 pm to 6:30 pm.

23rd October(Saturday)
	A problem was occurring in the program while executing the program.
	All the team members sat in the OSL and worked on that from 8:30 to 11:00 am.

24th October(Sunday)
	Completed the overall work of the project for stage I submission.

25th October(Monday)
	Had a meeting of the team with the group coordinator to decide what to do next.
	Even read the other parts made by the other teams to understand what logic they had developed.

27th October(Wednesday)
	Started working on writing the code for checking the validity of the email id given by the user.
	Googled what all was considered valid while writing an email id.

30th October(Saturday)
	Completed the program code for checking the validification of the email id.
	Further started working on the program code for making a Fixed Deposit Account for the customers.

2nd November(Tuesday)
	Completed the program code for making a Fixed Deposit Account for a customer.
	Further working on the code for if the customer wants more than one Fixed Deposit Account.