Back    Next

Events in 1994

48.     On 19th January 1994, the Tariff notification was amended. The definition of generation and deemed generation were altered to include backing down ordered by the MSEB .

 

49.     On 5th February 1994: Chairman, MSEB  wrote to the Special Secretary (Power) Government of India stating that “

“Sub:  Reservation of ‘tariff issues’ in the light of GOI notification dt. 30/3/1992 in respect of Dabhol Power Project.

The Dabhol project tariff is a negotiated tariff and not based on two part tariff indicated in the guidelines.

In the absence of the required notification, there is doubt whether we would be able to avail the benefits of the negotiated terms of the P.P.A. It may also lead to legal tangles which could cause delays in meeting the milestones of the project. I would be grateful if you could look into the matter and resolve these issues”

 

50.     On 10th February 1994, a Guarantee was signed by the Government of Maharashtra to irrevocably and unconditionally guarantee to pay to DPC any and every sum of money which MSEB is liable to pay to DPC under the PPA. Further  it also agreed to indemnify DPC against any loss by the Company “by reason of the invalidity, illegality or unenforceablity of the Guarantee of its provisions or the PPA”.  The State of Maharashtra has waived its Sovereign Immunity as well right of immunity on all its present and future assets. The guarantee is governed by English Law.

The relevant clauses of the said Guarantee are as follows: 

“Guarantee of MSEB Payment Obligations: The Guarantor hereby irrevocably and unconditionally Guarantees to the Company (as  a secondary obligor) to pay to the Company, within 7 calendar days  following submission by the company of a demand in accordance with Clause 1 (B), any and every sum of money which MSEB is liable to pay to the Company under or pursuant to the PPA and shall fail to pay in accordance with the terms of the PPA.

Indemnity: The Guarantor undertakes, as primary obligor, to indemnify and keep indemnified the company against any loss sustained or incurred by the Company by reason of the invalidity illegality or unenforceablity of any of this Guarantee or the provisions of this Guarantee or the PPA and the amount of such loss shall be the amount which, but for such invalidity, illegality or unenforceability, the company would otherwise have been entitled to recover hereunder or thereunder”. 

Governing Law : The rights and obligations of the parties under or pursuant to this Guarantee shall be governed by and construed  according to English Law”. 

Sovereign Immunity: The Guarantor unconditionally and irrevocably: agrees that the execution, delivery and performance by it of this Guarantee constitute private and commercial act rather than public or governmental acts; agrees that, should any proceedings be  brought against it or its assets in any jurisdiction in relation to this Guarantee or any transaction  contemplated by this Guarantee, no immunity from such proceedings shall, to the extent that it would otherwise be entitled to do so under the laws of India, be claimed by or on behalf of itself or with respect to assets....waives any right of immunity which it or any of its assets now has or may acquire in the future in any jurisdiction..”

(All emphasis supplied)

 

51.     On 15 February 1994, GOM wrote to GOI that:

“The main issue, of course, is that the tariff proposal in the Dabhol Project deviate from the GOI's tariff notification. It is now necessary for the CEA to issue a suitable amendment under Section 43-A of the Electricity Supply Act. MSEB apprehends that unless such an amendment is issued, the PPA itself may run into legal difficulty”

 

52.     On 19th April 1994, the Department of Economic Affairs, Ministry of finance, wrote to Ministry of Power about their concerns about the proposed counter guarantee. In particular, inter alia, their concern was directed at the absolute magnitude of the proposed liability that the GOI would be liable. This could amount to a potential total exposure of Rs. 2 lakh crores. Further, that the risk of these guarantees being invoked was not too farfetched.

 “..The total exposure on the Government of India counter guarantees may be around $ 2.5 billion (annually), for the 7 fast track projects;  around Rs. 10,000 crores......” ”...risk of the counter guarantees being invoked was not unreal given that SEBs had been defaulting in payments...”  

At this stage, it is now recorded that, inter alia, the “ Ministry of Finance was not concerned whether the cost of power was acceptable”.

All parties, especially the Ministry of Power and the CEA proceeded on the basis of the Finance Secretary’s statement that the cost of Power was reasonable. 

The note also goes on to say that the questions like the backing down of much cheaper power stations, whether the foreign exchange risk is acceptable, etc. ought to be checked by the Ministry of Power.

 

53.     On 12th May, 1994, in a “Secret” note prepared for the Cabinet of India, seen and approved by the Minister for Power,

 “Thereafter DPC obtained various clearances, including clearance by Central Electricity Authority (CEA) and entered into a Power purchase agreement with the MSEB”

i.e. even the Cabinet of India was led to believe that the CEA’s sanction was already granted.

 

54.     The Dabhol project came under pointed scrutiny in the 26th Report of the Standing Committee on Energy. In written submissions the CEA stated that “In November 1993, CEA accorded clearance to the Dabhol power project subject to  fulfillment of certain conditions.” It further recorded

“The tariff was finalised in December 1994.”

The Dabhol Power Company lied when it informed the subcommittee that

“ during the initial phase of the negotiations with MSEB the Dabhol Power Company neither insisted nor expected any guarantee on payment obligations, except, maybe, from  Government of Maharashtra. However following the announcement of the policy of counterguaranteeing on payment of obligations SEBs announced by the Government of India, the company took advantage of it.

 

The Committee expressed grave reservations about the Dabhol project in its Recommendations and Conclusions particularly in

·       respect of its excessive cost(6) ;

·       guarantee of offtake implying backing down of existing power generation making them inefficient and financially non-viable ( 7) ;

·       unjustified counterguarantee (8) ;

·       lack of transparency caused by confidentiality clause (11) ;

·       and absence of a fuel policy (13).

 

55.     On 24th June 1994, the CEA now (in WP 2456 of 1996) claims to have met to approve the project in direct contradiction, inter alia, to its decision taken in the 12th November meeting, in absence of any more information or any further consideration of the project after November 1993.

 

56.     On 24 June 1994, a State Support Agreement signed between GOM and DPC. This agreement too is governed by English law. The state, inter alia, has waived both sovereign immunity as well as immunity on all its assets !! Some relevant clauses include

“GOVERNING LAW

The rights and obligations of the parties under or pursuant to this Agreement shall be governed by and construed according to English Law.

SOVEREIGN IMMUNITY

GOM unconditionally and irrevocably:

agrees that the execution, delivery and performance by it of this Agreement and those agreements and other documents comprising the Security Package (as defined in the Power Purchase Agreement) to which it is a party constitute private and commercial acts rather than public or governmental acts;

agrees that, should any proceedings be brought against it or its assets in any jurisdiction in relation to this Agreement or any transaction contemplated by this Agreement, no immunity from such proceedings shall be claimed by or on behalf of itself or with respect to its assets; Waives any right of immunity which it or any of its assets now has or may acquire in the future in any jurisdiction, ...”

 

57.     On 13/7/1994 WP 1702 0f 1994, Ramdas Nayak and another versus the Union of India and others was filed. The CEA was not a party in the case, nor was the concurrence/ clearance an issue. The challenges in the case were the following:

·       That there should be no implementation of core sector projects without transparency and fairness;

·       On the lack of tenders;

·       That the guarantees violate Arts. 292 and 293 of the Constitution of India;

·       The World Bank objections

·       That the project be reviewed by experts and finally that

·       That a certiorari be issued against MOU and PPA

 

58.     On 14th July 1994, the purported clearance of CEA to Enron was issued. The document states: “.

“ Since the conditions to be fulfilled by M/s. DPC stand complied with, the Dabhol CCGT project is hereby accorded clearance by the Central Electricity Authority” 

    The document does not mention any approved project costs, nor any approved financial package. It is evident that the letter is ministerial. It does not refer to any meeting or any further consideration of the project after November 1993.

    All parties involved, including the GOI, GOM, DPC and the Ministry of Power had claimed that the letter of 26/1/93 was the clearance. After filing of the writ petition under appeal, the parties have changed their stand on this issue, contending that this letter dated 14/7/94 is the clearance.

 

59.     On 19.8.94, the Hon’ble High Court at Bombay, gave its decision in the above mentioned case of Ramdas Shrinivas Nayak v. Union of India. Extracts from the Judgment are set out below.

 

“..The duty of the court in case of judicial review is to confine itself to the question of legality, rationality and propriety of decision-making process.”

“It is not for the Courts to determine whether a particular policy or a particular decision taken in the fulfillment of that policy is fair. It is concerned with the manner which those decisions have been taken”

“It is not for the Court to determine whether a particular policy or a particular decision taken in the fulfillment of that policy is fair. The Courts should not enter into the merits of Government actions, more so, in economic matters unless the same is unreasonable and is not in public interest.”

    The Court’s observations included “Nothing was done secretly. There was total transparency at every stage of the negotiations. and further that

We may also make it clear that the petitioners have not alleged any malafides against the respondents. There is nothing to show that anybody was being favoured for any specified reason. The grievance of the petitioners is on the sole ground  of the failure to follow the usual procedure of inviting tenders, which as stated by us earlier, is not an invariable rule. In our opinion, in the present case it may not be an appropriate mode. Negotiations was the only appropriate mode which has been done in a most reasonable manner. The decision has been arrived at after long deliberations and discussions and after consideration of all relevant factors. We do not find it necessary to find any reason to interfere with the same in exercise of our extraordinary powers of judicial review under Article 226 of the constitution of India.

    The Hon’ble high Court held that, after “Applying above principles to the facts of the case,  “We do not find any impropriety in the Power Purchase Agreement entered into between the MSEB and Respondent No. 8, the Dabhol Power Company. Finalisation of a deal by negotiations, as has happened in the present case cannot, per se, be termed as illegal.”

(All emphasis supplied)

 

60.     On 22nd of August 1994, the GOI amends tariff notification, inter alia arrogating to itself the right to approve deviating tariffs.

 

61.     On 24th of August 1994, the Finance Secretary, GOI, in a letter to Power Secretary, GOI, in the 3 context of counter guaranteeing GOM’s obligations to DPC, stated that

“Average cost of generation: Rs. 1.24......Transmission and distribution (T+D) losses:  21.2%  against international norm of 6 to 7%......Size of potential liability: for 1000 MW plant, around  Rs. 3000 crores per year (around $ 900 Million per year for 1000 MW); around Rs. 12,000 crores per year for the 7 `fast track projects’ for over ten years....”

 

62.     On or about August, 1994, the Dept. of Finance, of the GOM had made the following comment, which too, was not incorporated, in a note being prepared for the cabinet about the Tripartite Agreement,

“It is true that, as stated in section 2 sub-section 8 of the agreement, as per the guarantee of the Central Government, whatever amount will be given by the Central Government to the company (DPC) will be directly deducted from the Reserve Bank account of the State Government. As regards this it can be only said that we will have to give up the rights conferred on us by the Indian Constitution”.

 

63.     On 16th of September 1994 a Tripartite agreement signed between GOI, GOM, and the Reserve Bank of India. This agreement guaranteed payments to DPC to the tune of Rs. 1500 crores a year by the GOI, in the event that GOM defaulted in its obligations. The RBI is to deduct any such amounts from the state’s share of central revenues. The limit was to be indexed to the rate of inflation, but rising a minimum of 7% a year. The total minimum exposure of the GOI is to the tune of at least Rs. 35, 000 crores plus U$ 300 million.

The GOI “waives any right of immunity which it or any of its assets now has or may acquire in the future in any jurisdiction.

and “consents generally in respect of the enforcement of any judgment or award against it in any such proceedings to the giving of any relief or the issue of any process in any jurisdiction in connection with such proceedings (including, without limitation, the making, enforcement or execution against or in respect of any assets whatsoever irrespective of their use or intended use of any order or judgment that may be made or given in connection therewith);.... “assets” shall be taken as excluding present or future “premises of the mission .....and ...military property or military assets...”

 

64.     On 22nd September, 1994 the CEA wrote to the Ministry of Power that

“..that the CEA before granting techno economic clearance has to determine whether the total project cost as well as the tariff proposed by the private sector developer are reasonable.”

 

65.     On 23rd September, 1994, Dr. Kirit Parikh (Member, renegotiating team of GOM in Nov. 1995) wrote to PM, GOI  warning of a

“... serious financial crisis... if “all seven fast track projects are given 90 per cent load factor (LF) guarantee and a price of 7 US cents per unit”  

He goes on further to say that this would

 “.... disrupt our growth process for years to come.....”

He also wrote that 

“The 90 per cent load factor guarantees offered to foreign plants such as Enron’s Dabhol Plant, would involve hundreds of crores of hidden burden per year”

(Emphasis supplied)

After renegotiating the deal , the team of the GOM, Dr. Parikh being a member,  awarded a 90% load factor guarantee for a substantially larger project i.e. a guarantee for over 3 times the project that the concern was raised for..

 

66.     On 7th of December 1994, the MSEB wrote to the Ministry of Power that

“as indicated by them (DPC)...... If naphtha is available and can be obtained at lesser price than distillate, DPC  will use Naphtha as the situation exists. They (DPC) have designed the plant and plant equipment to accommodate either fuel”

The conversion of the plant to one capable of using naphtha has been touted as one of the major advantages of Renegotiations. (Nov. 1995). Further MSEB has now also to pay DPC about Rs. 40 crores for the conversion of the plant to one capable of running on Naphtha !!!!

 

67.     The non consideration of the crucial question of costs was underscored by the repeated attempts to evade responsibility on the question  by various concerned authorities. On or about 22 December, the ministry of Power requested CEA to confirm reasonableness of capital costs

 

68.     On 23rd December 1994, the CEA in response states that

“since the cost of power has been found reasonable by the Ministry of Finance and since cost of power is derived from capital cost, capital cost ought to be considered reasonable.”   (Emphasis supplied) .

Obviously the CEA has not approved any capital costs, nor seen figures on which it could express its opinion. It is also implicit that the CEA did not find the cost of power reasonable.

Further, the MOF had itself recorded on 19/4/94, that “Ministry of Finance was not concerned whether the cost of power was acceptable”

Back    Next