INDIA
DABHOL
POWER PROJECT
Introduction
1. In July 1992, ENRON power Development
Corporation, (ENRON, USA) and the Maharashtra State Electricity Board (MSEB)
entered into a Memorandum of Understanding for Enron to set up a 2550 MW power
Station to build, own and operate basis, at Dabhol, about 150 miles South of
Bombay in the state of Maharashtra. This proposal was subsequently scaled down
to 2015 MW and is referred to in this note as the project. The project would
run in base load on natural gas, imported from Qatar in the form of Liquefied
Natural Gas (LNG). The size of the project in base-load operation, matches
output of one LNG production train. A two stage development is envisaged stage
1 involves construction of 690 MW, stage 2 an expansion to about 2015 MW,
consisting of 3 X 635 MW combined cycle units and 110 MW additional gas turbine
peaking capacity. Stage I is scheduled to be commissioned in the first quarter
of 1996 (assuming financing is arranged by the end of 1993), running initially
on distillate fuel oil. Stage 2 is scheduled to be commissioned in 1998, if the
financing and the contract for the supply of LNG can be finalized by the end of
1993.
Power
Purchase Agreement (PPA)
2.
The power purchase agreement (PPA)
provides for separate capacity and energy charges. MSEB would pay not only the
capacity charge but also the energy charge if the generation (due to MSEB's
despatch) does not reach the agreed minimum level (currently envisaged by ENRON
to be 80-85%). ENRON has indicated that it is prepared to guarantee a 90%
availability and its calculations assume dispatch at 90% plant load factor.
Since the plant is designed to consume the output of one LNG train and in light
of the PPA provisions, MSEB will have no option but to run the plant in base
load with minimal variation.
Power
Market
3. The addition of a 2015 MW station, in
forced base-load operation, would place a significant constraint in MSEB's
power system. System simulations show that while the project would provide
additional generation to help most increasing loads in peak periods, it would
displace lower cost coal-fired generation in the off-peak periods.
4. The Western Region system and India as
a whole have surplus generation capacity in off-peak periods (8-10 hours during
night time. Although the output of coal-fired stations is reduced during the
off-peak periods within occupational constraints, system frequencies commonly
exceed 50 Hz off peak, a concrete sign of surplus capacity. The imbalance between
base load generation (mainly coal) and peak-to-intermediate load generation
(mainly hydro supplemented by natural gas in combined cycle generation) has
worsened steadily during the 1980s and is likely to worsen further in the 1990s
and possible even beyond. Surplus coal-based power in the off-peak periods is
likely to continue in the foreseeable future.
5. Since MSEB's system cannot fully absorb
the output of the project in off-peak periods, MSEB have to sell surplus LNG
based power to other states. At best, MSEB may be able to sell coal-based power
in the Southern Region, at or close to its variable generating cost, in
off-peak periods. As a result it would
incur financial losses. LNG generation at a variable cost of about paise
150/kwh would displace coal-based power costing paise 30/kwh. This loss,
adjusted to economic terms, would have to be included in the economic analysis
as a project cost and thus reduce project benefits.
Market
for LNG Power In India
6. Natural gas-fired combined cycle
stations provide an attractive option for intermediate to base load generation.
In the Indian system, given the current and the projected availability of lower
cost coal fired base load generation during off-peak periods, combined cycle
stations are economically attractive mainly in intermediate load service. The
availability of natural gas constraints currently the use of gas for power
generation. Imported LNG has a potential market niche supplementing domestic
natural gas. Targeting the Dabhol Project to take advantage of this niche would
require modifications in the project design and size as well as in the PPA.
Given the relative high cost of LNG compared to local natural gas, a comparison
between LNG based power and coal based power in intermediate load generation
would still be necessary to ensure that this indeed meets the least-cost
condition. Due to its higher capital cost, a coal fueled station is generally
not competitive in intermediate load service, but the high cost of LNG
increases coal's competitiveness.
Macro-economic
considerations
7.
The implementation of the project
would place a significant long-term claim on India's foreign exchange
resources. The estimated annual fuel cost is about US $ 500 million, subject to
escalation as provided for in the PPA (a fuel cost pass through to MSEB is
envisaged). Contractually, capacity payments in foreign currency would start at
about US $ 175 million (70% foreign exchange portion only considered here) in
1996 and escalating at 5% per annum, reaching US $ 400 million in 2015.
8. Bank projections indicate that (a) the
current account and external reserve positions, and the external debt/expert
ratio would improve (b) the debt
service ratio would rise initially, but fall to 22% in FY 1998 (compared to 26%
in FY 93) and (c) foreign reserves in FY 98 would be at over 10 $ billion or
less annual foreign exchange claims are considered affordable by India in this
scenario. For example, in year 2000, fuel import for the project would account
for about 1.2% of India's merchandise imports, capital service would account
for about 1.7 % of India's merchandise exports. There is down side risk of much
lower than the projected 5.6% annual GDP growth; and a much less favorable
balance of payments and reserve position could emerge.
9. Most critical for the project with a
non-tradable output (and with no direct foreign exchange earnings) is the
relative growth of India's exports and imports. Bank projections show export
growth consistently exceeding the growth of imports, contributing to the
relative base case set of indicators outlined above. Import demand depends on
the pace of further liberalization, and on the performance of the energy
sector, in particular the domestic production of oil and gas. Price of oil is
an important variable; a Bank sensitivity analysis shows that a 33% increase
could lead into foreign reserves declining to half the projected reserve. While
such risks reinforce the need for prudent macro-economic policies and vigorous
export promotion, the project would even in that scenario still be considered
affordable for India.(1)
10. Assuming
that the alternative would be to build additional coal-fired stations using
local coal, the outflow would be
limited to debt service for foreign borrowing, foreign exchange. Such foreign
exchange outflow would be significantly below those of ENRON project (about
30-40% only of the Enron outflow) and would be even lower depending on the
extent of domestic manufacturers' participation in the equipment supply. The
foreign exchange outflow resulting from the development of coal-fired
generation using imported coal would be much closer to the outflows of the
ENRON project (the difference would depend on the source of equipment and the
possibly different escalation of LNG and coal prices).
11. It has been argued that in the absence of
the project, India would not implement the domestic or the imported coal
option, due to financing constraints. True additionally of the project is
limited to the foreign equity, even as concerns that component, Enron’s
partners (GE and Bechtel) might well invest in coal based power projects in
India in case the project does not proceed. ENRON is unlikely to participate in
coal projects, but may be interested by another gas-based project. The major
part of the project financing proposed to be provided by the Bank, US Exim Bank
and domestic capital market, should be available to finance reasonable
alternative projects, such as a series of 500 MW coal projects using imported
coal. Not proceeding with the project may somewhat delay power development, but
it is unlikely to cause a lasting setback to India's private power
program.
______________________________________________________________________
1.
India should according to the considerations, afford to commit to number of
power projects of this size or smaller private power projects in the 1990s. The
main question then becomes which projects it should pursue and whether LNG
base-load power is among the high priority options.
Cost
and value of LNG Power
12. ENRON
indicated that the total cost of power, in base load generation at 90% plant
load, is about US cents 7.0/kwh, of which about US cents 3.3/kwh is for
capacity. Assuming industrial sales in areas close to the project location and
on additional investment of 20% for transmission and distribution and assuming
10% for system losses, the average cost at the consumer level would at the
minimum be US cents 7.4/kwh. This corresponds to about Rs. 2.4/kwh in 1993
prices. These figures do not include import duties and taxes on equipment and
LNG. The former has been reduced to 20% in India's FY 94 budget, the later is
understood to be at 16%. Using these figures, the resulting retail revenue from
LNG power would have to be Rs. 2.4/kwh in 1993 prices, equivalent to Rs.
4.6/kwh in 1998 prices, with no provision for administrative and other MSEB
overheads (or cross-subsidization of agricultural and residential consumers,
para. 14).
13. The cost of LNG based power is comparable
to that of diesel generation and lower than that of diesel pumping. The
willingness to pay for electricity by industrial consumers has been estimated
at about Rs. 2.2/kwh in the Western region and Rs. 2.4/kwh in Bombay in the
second Maharashtra appraisal report, below the cost of LNG power. The Bank's
standard project economic analysis concludes that the project is not viable.
The project therefore would have to be justified as a special effort to meet
the electricity demands of consumers expressing a willingness to pay higher
tariffs for guaranteed and/or additional supply at system peak periods.
However, it remains to be established that a demand for such power exists.
14. Electricity prices given in 1998 prices
above demonstrate the need for substantial tariff adjustments for MSEB. Its
current average revenue is about Rs. 1.4/kwh, the revenue from the most
lucrative industrial consumers is in the
Rs. 2-2.5/kwh range. Prices for industrial consumers would at the
minimum have to be doubled in nominal terms to recover the cost of LNG power.
This indicates annual increases of about 15-20% against the Bank's 5-6%
inflation estimates. It should be noted that to the extent that the industrial
customers actually take LNG power. However, the above tariff would not provide
for cross-subsidization hence an across the board adjustment instead of a
special LNG power tariff for specified consumers would be needed.
Load
Forecasts
15. System
simulations referred to in the above discussion use CEA load projection for
Maharashtra. The projections assume an annual load growth of over 7% in the
1990s and about 6% in the following decade. This projection is higher than the
forecast used in the appraisal in the 2nd Maharashtra Power Project. The later
was based on Maharashtra's estimated capacity in supply, which due to financial
constraints was judged insufficient to meet CEA's forecast.
16.
MSEB maintains that CEA's projections is too low, on the basis of pending
applications from industries for additional supply not considered in the CEA
projection. Such application amount to about 4100 MW. MSEB's assessment is that
about 50% of these applications would materialize, thus increasing the peak
load by 2100 MW by 1997 at a 77 % load factor. This would absorb all LNG power
and eliminate the projected surpluses. Should this load scenario materialize,
surpluses would indeed diminish. However, this would not invalidate the
conclusion that on LNG based power
plant operating in base load is not the least cost option for expanding power
supply.
17. The suggested load increase is unproven
and the proposed high forecast is not a suitable basis for evaluating the
project. Three points warrant attention regarding the proposed high forecast.
First, the full additionality of the loads in pending applications is
questionable and the resulting growth rate for industrial electricity
consumption is unproven. MSEB's industrial sales in FY 93 were about 16400 Gwh
and are projected to increase to about 22300 Gwh in the CEA forecast, adding
about 6000 Gwh MSEB's proposed additional load to be connected by that year
corresponds to 12000 Gwh. Under this assumption industrial load would double,
i.e. grow at an average rate of about 20% for 4 years, compared to CEA's already respectable 8% average annual
growth.
______________________________________________________________________
2.
Given the large size of the project to MSEB system, time allocation of the
output to the most lucrative consumers of course somewhat questionable. The
locational advantage is clear the project will generate power not far from the
main load centre in Maharashtra, the Bombay metropolitan area.
Second,
the willingness of the applicants on MSEB's 4100 MW list to pay the above
mentioned price, involving more than doubling the current industrial tariffs,
has not been tested. Applications may well reflect expectations of the relative
low electricity prices continuing. Before a high forecast could be adopted as the basis of the analysis of the new
state-wide forecast (involving the review of CEA forecasts and pending
applications) would need to be undertaken, taking price explicitly into account
in the forecast. Third, MSEB is unable to connect the new load gradually
between 1993 and 1997 as it does not have additional generation capacity, The
load is unlikely to wait until 1996-1998 and then come in over 1-2 year period;
a more gradual increase is likely.
Conclusions
:
18 Although
the ongoing review of the methodology would require marginal adjustments in
some of the assumptions, it is highly unlikely that they would change the
results
of
the analysis. The main conclusions of the analysis are summarized below :
(a) The project is not a least-cost choice
for base load power generation compared to Indian coal and local gas. Even if
domestic fuels are not available, imported coal would be the least-cost option
for base-load generation for MSEB with current environmental standards. The
additional requirement of fuel-gas desulphurization would narrow coal's
advantage, but in all likelihood not eliminate it; an environmental premium
would be required to close the gap. In addition to lower fuel cost, the coal
alternative is more attractive due to its flexibility, capacity can be added in
500 MW units in steps to meet the growing demand instead of a 2,000 MW in 1998 in the project;
(b) The unique features and risks of this
LNG-based project (large minimum consumption, dependence on one power generator
and on one LNG supplier) need to be considered; they offset LNG's environmental
benefits over coal. The LNG price
escalation cost is still to be confirmed for the project; international
practice is to be the price of LNG to oil or coal price;
(c) ENRON's current proposal would
require MSEB to dispatch the plant as a base load unit at 80-85% minimum plant
factor( referred to as plant load factor, PLF, in India). This would prevent
the operational flexibility of a combined cycle plant,
(d) Stipulations of MSEB power
operations indicate that the project would add more capacity than needed to
meet the projected load growth in 1998 and would also result in uneconomic
plant dispatch (lower variable cost coal power would be replaced by much higher
variable cost LNG power). This would adversely affect the economic viability of
the project and place a heavy financial burden on the MSEB; and
(e) Substantial adjustment in
electricity tariffs would be required to recover cost of the project from the
consumers and to safeguard MSEB's financial position. Given the large share of
the project in MSEB's power supply in the initial years, across-the-board
adjustment would be required. Adjustments limited to special industrial
consumer categories would not be sufficient as their capability to continue to
cross-subsidize, by paying more than the already high cost of LNG power, would
be limited.
April 30,1993.